RPS Savana Faridabad

Posted By indiaspaces . on 03 Nov 2011
Members (144) | Comments (254)

 

RPS Savana Faridabad (Price)

Accommodation

Area(sqft)

Rate (per sq.ft.)

Booking Amount

2BR, Drawing/Dining, Kitchen, Toilets & Balconies

1250 sq.ft

Rs. 2350

10% (Approx)

2 BR,Study Room, Drawing/Dining, Kitchen, Toilets & Balconies

1303 sq.ft

Rs. 2350

10% (Approx)

3BR, Drawing/Dining, Kitchen,Toilets & Balconies

1590 sq.ft

Rs. 2350

10% (Approx)

3 BR, Utility Room, Drawing/Dining, Kitchen, Toilets & Balconies

1791 sq.ft

Rs. 2350

10% (Approx)


 

4+1 BR & Pent House in International Specification

Accommodation

Area(sqft)

Rate (per sq.ft.)

Booking Amount

4 BR, Utility Room, Drawing/Dining, Kitchen, Toilets & Balconies

2360 sq.ft

Rs. 2800

10% (Approx)

4 BR, Utility Room, Lounge, Living Room, Dining Room, Kitchen, Toilets & Balconies

2380 sq.ft

Rs. 2800

10% (Approx)

4 BR, Utility Room, Lounge, Lobby, Living Room, Bar, Dining Room, Kitchen, Toilets, Home Theatre Room & Balconies 3560 sq.ft. Rs. 2800 10% (Approx)
Comments
Savana status - ( RPS Savana Faridabad )
Posted by 13 Jan 2010
Hi Jitendra, Raised concern over slow progress of construction. Here is response email I received from company. Just FYI for you to update. ------------------ Dear Sir, Please refer to our telecon 11/01/2010. In regard to status of construction at site, we would like to update you that at present we are working on 11th Floor Roof slab casting of Tower Sapphire Berry - 10. There are total 17 roof slabs in your tower. Construction work is in progress on almost every tower. More than 22 towers have crossed the stage of 7th floor roof slab and in many towers last floor roof slab casting has been completed. In regard to schedule of construction activities, we would like to intimate that construction work of the project has been allocated to all our contractors with clear instruction of completion period. It is our earnest endeavour to offer the possession of units in project 'SAVANA' from Nov./Dec. 2010 onwards. We seek co-operation of all our esteemed customers for successful completion of project 'SAVANA'

Related Comments    Reply to comment    Post New Comments
RPS Savana - ( RPS Savana Faridabad )
Posted by Anshuman Singh 05 Jan 2010
Are the industries adjacent to SRS of polluting kind and are these going to have any adverse effect on the quality of life in RPS Savana ?

Related Comments    Reply to comment    Post New Comments
Findings after neharpar area visit - ( RPS Savana Faridabad )
Posted by Dhirendra Singh Jadon 27 Dec 2009
Dear indiaspacesji, I visited RPS Savana site and near by areas and below are my findings. 1. Construction work on RPS savana site is on full swing for 2-3 bedroom flats, located backside of the site. I got to know from the representative there, because of Vaastu, they will complete the back side work first and then start work on other buildings. Not sure about the real truth. 2. Looks like Kheri road widening has started. they have started construction of cemented road. However, that is also in bad shape. Hope to see completion in next 1 year. 3. Badarpur bypass is also under consturction. I could see that local people have started demolishing their houses (which are unauthorized). 4. Sector roads work have not started yet. Savana representative had no answer on that. Please let us know if you have more updates. Thank you

Related Comments    Reply to comment    Post New Comments