Omaxe New Heights Faridabad

Posted By indiaspaces . on 09 Nov 2011
Members (144) | Comments (632)

POSITIVES - Low Price, Less Wastage Floor Plans, Reputed Developer, Limited Units 

NEGATIVES - Abnormal Delays, Bank Funding Not Available, External Infrastructure Dependent Location 

OMAXE NEW HEIGHTS, Sector 78, Faridabad is one of the most affordable group housing in the region.

The project had all licenses and map approvals and was originally launched as Omaxe Spa Vlillage.  

Post global meltdown, around 2 years back, company decided to change sizes and relaunch a part of it as Omaxe New Heights. 

Company was unable to deposit the EDC/IDC till 2011 and was paid only in the second half of 2011 which also marked the sanctioning of building plans.

http://indiaspaces.com/down/1353_omaxe_new_heights_.jpg

Meanwhile Haryana Govt increased the EDC / IDC to almost double, something which was not anticipated. Around this time the license of the project has also expired. Now unless the new EDC/IDC is paid to department, the license would not be renewed, sanctioned maps would not be handed over to company and no bank loans would happen.

People totally dependent on bank loans would actually have no choice then to exit the project either by way of refund or resale in open market. 

Company might subsequently sell these flats at higher prices.

It may even ask all other customers to pay increased EDC. For this INDIASPACES had suggested management, that the money should be received in a separate account specifically for EDC only.

Comments
ONH - Empire - ( Omaxe New Heights Faridabad )
Posted by asha 24 Jul 2012
Has anyone got enhanced EDC/IDC calculation from Omaxe? Seeing some related threads, I feel 205/sqft for enhanced EDC/IDC is quite steep as compared to other projects.
ONH - ( Omaxe New Heights Faridabad )
Posted by Hemant 26 Aug 2012
yes there is some problem the way omaxe has calculated Enhanced EDC. the enhanced EDC demand from ERA is for Rs.155/- per sqr feet where omaxe has taken more than Rs.200/- per sqr feet from us. we need to write back to Omaxe on this as i shall be doing the same. the raise was for enhaced EDC i think they have increased IDC etc proportionately which omaxe should not.

Related Comments    Reply to comment    Post New Comments
Triumph Omaxe New Heights - ( Omaxe New Heights Faridabad )
Posted by Manav 24 Jul 2012
I visited Triumph and saw dirt being cleared for the sector road, couldn't confirm if that will connect BPTP bridge. In Triumph, in the stairway, tiles being laid and front railings are being provided. SPA village and Era Group towers stand plastered for finishing.

Related Comments    Reply to comment    Post New Comments
ONH Construction update - ( Omaxe New Heights Faridabad )
Posted by D.P.Dabas 23 Jul 2012
Work is going on in full swing in all towers of ONH. In bloomberg tower 8th floor is reached. premimum has touched 10 lacs. Good thing is that Master Road connecting ONH being constructed by HUDA is now visible near the society. Crossing village to reach ONH site may not be required in coming months.

Related Comments    Reply to comment    Post New Comments
ONH - ( Omaxe New Heights Faridabad )
Posted by 22 Jul 2012
Dear Jeethuji, Why people (agents) ask for time of 2 months when two party agree for sale of flats? I don't find any reasons for delay. Why is it so?

Related Comments    Reply to comment    Post New Comments
ONH road - ( Omaxe New Heights Faridabad )
Posted by Rohit 19 Jul 2012
Did anybody visited ONH site recently? If yes, please update about sector road leading to BPTP bridge from Omaxe New heights?
Becoming Worth Living - ( Omaxe New Heights Faridabad )
Posted by Manav 01 Aug 2012
Not before mid-2015....this is just my opinion.
ONH status - ( Omaxe New Heights Faridabad )
Posted by Rohit 25 Jul 2012
Any idea, when ONH will be completed. And finally fit for living?
Triumph Omaxe New Heights - ( Omaxe New Heights Faridabad )
Posted by Manav 24 Jul 2012
I visited Triumph and saw dirt being cleared for the sector road, couldn't confirm if that will connect BPTP bridge. In Triumph, in the stairway, tiles being laid and front railings are being provided. SPA village and Era Group towers stand plastered for finishing.
ONH Construction update - ( Omaxe New Heights Faridabad )
Posted by D.P.Dabas 23 Jul 2012
Work is going on in full swing in all towers of ONH. In bloomberg tower 8th floor is reached. premimum has touched 10 lacs. Good thing is that Master Road connecting ONH being constructed by HUDA is now visible near the society. Crossing village to reach ONH site may not be required in coming months.

Related Comments    Reply to comment    Post New Comments
ONH Chelsea/Empire - ( Omaxe New Heights Faridabad )
Posted by nag raju 13 Jul 2012
I have received demand letter for Chelsea Tower (On casting of 7th Floor) and Empire tower (on casting of 5th Floor + PLC)

Related Comments    Reply to comment    Post New Comments
ONH / Empire Tower - ( Omaxe New Heights Faridabad )
Posted by 10 Jul 2012
I did received the demand for 5th floor. Visited site on 1st July and the progress is visible.

Related Comments    Reply to comment    Post New Comments
ONH Bloomberg demand - ( Omaxe New Heights Faridabad )
Posted by Rohit 10 Jul 2012
I have received demand of 293485.88 ruppees for ONH-Bloomberg tower 2BHK+Study. last date for the same is 25 july 2012 ( ON CASTING OF FIFTH FLOOR ROOF + PART OF ADDITIONAL CHARGES + PLC )

Related Comments    Reply to comment    Post New Comments
ONH - Empire - ( Omaxe New Heights Faridabad )
Posted by asha 09 Jul 2012
Hello, Has anybody recd demand for casting of 5th floor roof and whats the progress of construction? Thanks - Amit
ONH Chelsea/Empire - ( Omaxe New Heights Faridabad )
Posted by nag raju 13 Jul 2012
I have received demand letter for Chelsea Tower (On casting of 7th Floor) and Empire tower (on casting of 5th Floor + PLC)
ONH / Empire Tower - ( Omaxe New Heights Faridabad )
Posted by 10 Jul 2012
I did received the demand for 5th floor. Visited site on 1st July and the progress is visible.
ONH Bloomberg demand - ( Omaxe New Heights Faridabad )
Posted by Rohit 10 Jul 2012
I have received demand of 293485.88 ruppees for ONH-Bloomberg tower 2BHK+Study. last date for the same is 25 july 2012 ( ON CASTING OF FIFTH FLOOR ROOF + PART OF ADDITIONAL CHARGES + PLC )

Related Comments    Reply to comment    Post New Comments
ONH - ( Omaxe New Heights Faridabad )
Posted by asha 25 Jun 2012
When compared to other projects, the total EDC/IDC of 167(old)+205(new) psft looks quite high.